Development / 07
Convention Center Expansion
San Diego Convention Center, downtown bayfront
The funded work at the Convention Center is repair work. A February 2026 City resolution puts $21,402,788 toward the existing building's infrastructure; it does not authorize building a larger convention center. Physical expansion is a separate undertaking.[19]
- Documented status
- FY2026 repair funding approved; physical expansion unresolved in the reviewed record
- Evidence basis
- Mixed evidence; see distinctions below
- Originating coverage
- AMSI ·
- Sources checked / profile published
01
Where the approved money goes
Roof, power, electrical and central-plant work are the purposes of Resolution R-316636. The Council adopted it on February 23, 2026, with final passage February 26, directing Measure C hotel-tax revenue to the existing facility.[19]
Voters approved Measure C in March 2020, but litigation delayed collection of the additional hotel tax until May 1, 2025. Under the resolution, 59% of that additional tax goes to the Convention Center Revenue Account.[19]
- FY2026 funding
$21,402,788 is the approved allocation, the exact figure behind AMSI's description of over $21 million.
Confirmed in cited source · Source ↗
- West roof work
$7,500,000 covers engineering, design and construction.
Confirmed in cited source · Source ↗
- Central-plant work
$9,503,888 covers overhaul design and later replacement work; another $600,000 is for quality assurance and quality control.
Confirmed in cited source · Source ↗
- Generator and electrical work
$1,275,000 goes to the west generator and underground storage tank; $1,423,900 to transformers; and $1,100,000 to switchgear and panels.
Confirmed in cited source · Source ↗
02
A larger repair bill, not a larger building
Urgent repair needs run to nearly $120 million over five years, according to the Union-Tribune's February 24, 2026 report. The same report gives the more precise description of more than $118 million. These are two descriptions of the same near-term program, not separate bills.[11]
The longer horizon comes from a 2022 facility assessment: nearly $244 million in repairs and capital improvements over 25 years, rising to more than $452 million with inflation. AMSI's wording, up to $244 million+, obscures the difference between the time horizon and the inflation-adjusted cost.[11][20]
Boilers and chillers, electrical infrastructure, plumbing and roof leaks are among the reported problems in the 2.6-million-square-foot building. Fixing them supports continued event operations without, by itself, adding exhibit space.[11]
- Size of the existing facility
The facility is reported as 2.6 million square feet in coverage of the 2022 condition assessment.
Reported by cited source · Source ↗
- The five-year repair bill
The February 2026 report gives more than $118 million, also described as nearly $120 million. This is repair need, not a separate expansion appropriation.
Reported by cited source · Source ↗
- Needs over 25 years
The reported 2022 assessment puts needs at nearly $244 million. City staff quoted in February 2026 put the inflation-adjusted figure at more than $452 million.
Reported by cited source · Source ↗
03
Expansion still faces the land question
Enlargement was part of Measure C's Convention Center objective. February 2026 reporting, however, describes rising construction costs and unresolved control of the adjoining Fifth Avenue Landing leasehold. Its reported mid-2027 expiry concerns the lease, not completion of an expansion.[11]
A 2018 settlement also remained in place, according to the report, limiting public discussion or planning steps until the following year. The reporting and the repair resolution set no new expansion groundbreaking date. More convention capacity, tourism and opportunities for larger events are policy goals, not promised results.[11][19]
- What's holding up expansion
The February 24, 2026 report identifies rising costs and control of the Fifth Avenue Landing waterfront parcel.
Reported by cited source · Source ↗
- The lease date
The reported Fifth Avenue Landing lease expiry is mid-2027. It is not a date for an expansion to open in 2027.
Reported by cited source · Source ↗
Sources & further reading
AMSI supplied the starting list. These records and articles fill in the history and explain where later information changes the picture. The reference numbers belong to this profile.
Related profiles
Horton Plaza Repositioning
Horton Plaza's reinvention as an office-and-commercial campus reached a change of ownership before it reached a full reopening: the lender took over through foreclosure in August 2025. By July 2026, reporting described specific work on the park, theater access and permits, though not a reopened campus as a whole.
Redevelopment in lender ownership, with reported permit work and public-access obligations